Narayangadh–Mugling road to close five hours daily from Mangsir 13 for Tuinkhola landslide work
Chitwan's district administration will shut the Narayangadh–Mugling road each day from 11am to 4pm from Mangsir 13, until further notice, so landslide prevention work can begin at Tuinkhola.
This short update was prepared automatically from other news outlets’ reporting and has not yet been reviewed by an editor.
The Narayangadh–Mugling road section in Chitwan will be closed to traffic for five hours every day from Mangsir 13 (Sunday), so that landslide prevention work can go ahead at Tuinkhola, according to Ratopati and OnlineKhabar.
The District Administration Office, Chitwan, decided the road will stay shut from 11am to 4pm daily until a new notice is issued. Assistant Chief District Officer Ishwori Prasad Sharma said all types of vehicles will be stopped during these hours because of the risks the work may involve.
The Road Division Office, Bharatpur, is carrying out the work. It says landslides at Tuinkhola have not stopped, and it is looking for a long-term fix using special techniques. Since last year, landslides and road blockages have occurred in winter as well as the monsoon, which prompted the new approach.
The division says large boulders will be cleared to manage the slope, and a method called nailing will be used, in which steel rods are driven in to strengthen the affected area. Horizontal drains and bioengineering will be used to channel out water seeping from the hillside. Amit Kumar Sharma, chief engineer of the Bharatpur division, said bioengineering will be applied in two- or three-dimensional forms depending on the slope, and that nailing will be the main method.
The Tuinkhola work has been stalled since last Asoj and is now to resume. Sharma said work was also done at Tuinkhola when the road was blocked at Krishnabhir on the Prithvi Highway. It was paused to keep the route passable once Krishnabhir reopened.
Sharma said that, judging by the road's condition, it would have to be closed for at least 15 days to finish the work. A technical assessment will decide how long it must be closed, he said, and for now the daily closure applies until further notice.
He also said work at Ghoptebhir, near Mugling on the Prithvi Highway, would be finished by the next day, with the highway operating from the day after. Tuinkhola work will start once Ghoptebhir is done.
The administration said the Prithvi Highway, which runs from Kathmandu through Mugling and Aabukhaireni to Pokhara, will remain open. According to Ratopati, the administration apologised for the inconvenience to passengers and asked them to plan journeys accordingly. OnlineKhabar reports that it asked travellers to manage their travel times.