Rahughat Hydropower Project in Myagdi starts commercial output after 15 years
The 40 MW Rahughat project in Myagdi has completed its test period and begun commercial generation, about fifteen years after construction started, following contractor failures, a flood and other setbacks, say Nepali media.
This short update was prepared automatically from other news outlets’ reporting and has not yet been reviewed by an editor.
The 40-megawatt Rahughat Hydropower Project in Myagdi district has entered commercial production roughly fifteen years after construction began, according to OnlineKhabar, Ratopati and Setopati, which carried a report from the national news agency RSS dated 11 Mangsir.
The project is built by Raghuganga Hydropower, a subsidiary of the state-owned Nepal Electricity Authority. Managing director Ganesh KC said the test period has finished and commercial generation has started. He said testing began on 6 Asoj but ran longer than planned because the Kali Gandaki river flooded on 11 Asoj and damaged the powerhouse area at Tilkenichaur in Raghuganga Rural Municipality-3.
KC also listed natural disasters, Covid-19, customs problems, the effects of international conflict and a ban on extracting river materials from the Kali Gandaki as reasons for the delay.
The dam is located in Dagnam (ward 4) and Jhiko Phedi (ward 5) of the municipality. The project has a 6.27-kilometre main tunnel and two settling ponds. The powerhouse is beside the Beni–Jomsom road at Tilkenichaur. Project chief Rajbahadur Bista said an 11-kilometre access road and one Bailey bridge have been built. A switchyard and four towers with a transmission line link the plant to the 220 kV double-circuit Dana–Kushma line.
The power purchase agreement was signed in Chaitra 2075 BS, with a target of 240,593,034 units a year. India's Wapcos is the consultant.
The Authority signed a civil contract with the Indian firm IVRCL on 18 Kartik 2067 BS for Rs 2.5 billion. Under that contract, the original 32 MW plant would have begun producing in 2070 BS. The Authority cancelled the contract in 2072 BS because of IVRCL's weak finances, when physical progress stood at 12 percent after five years.
The Authority then restructured the project, raising capacity to 40 MW, and set up Raghuganga Hydropower in 2073 BS. Funding comes from a $67 million concessional loan from India's Exim Bank plus investment from the Authority and the government. India's Jaiprakash Associates won the civil contract on 6 Mangsir 2074 BS for about Rs 6 billion, with a 45-month target. Access road work began in Asar 2075 and tunnelling in Asar 2076. The main tunnel broke through on 15 Shrawan 2081. The deadline was extended several times, and the project finished within the fourth extension. India's state-owned BHEL holds the electromechanical contract, signed in Kartik 2076 for about $10.29 million.
Subin Shrestha, president of the Myagdi Chamber of Commerce and Industry, said Rahughat was the district's first and a government-funded project, seen as a gateway to hydropower development. He said ten projects have been completed in Myagdi since it began, and that locals are pleased it has finally started producing, even if late.