Investment Board approves two semi-reservoir hydropower projects

The Investment Board approved projects with a combined capacity of about 106 megawatts and a reported combined cost above Rs21 billion.

Onlinekhabar reported that the board approved the 58.9 MW Nar Khola and 46.72 MW Sani Bheri-3 projects at its October 9 meeting. It also set a February 2028 target for commercial generation from Arun-3 and called for steps to advance Upper Karnali construction. These are announced plans and targets; they do not mean the projects are already operating.

Source: https://english.onlinekhabar.com/investment-semi-reservoir-hydropower.html